DETAILS OF CONTRACT CONCLUDED FOR WORKS COSTING MORE THAN Rs.25.00 LAKHS INCLUDING STAGE PROGRESS     
 (Statement updated on  23.12.08.)
   

 

 

 

Sl

No

 

Name of workP

Sanctioned value of work with date of approval

 

Mode of tender Enquiry

Pre-bid tender status

 

Last date of receipt of tender

No of tenderers responded

Name of the tenderers technically

pre-qualified

Reference to work order

 

Name of the Contractor

Value of Contract

Period of contract

Dt. of commencement

Scheduled dt of completion

% of expre. status

Remarks

 

I . PLAN WORKS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.

Construction of Berth No.9

4000.00

21.7.2006

 

Publishing thro' News papers & Websites

04.8.2006

14.8.06

5

1.M/s.ITDC Pvt Ltd,

Kolkatta

 

17.11.06

M/s.ITDC ltd, Kolkatta

44.57 Crores

15 months

02.12.06

14-11-08

3226 lakhs

72.40%

Work in progress

2.

Dredging the dock basin infront of Berth.No.9

Rs.40 crores

09.04.2007

Publishing thro' News papers & Websites

 25.10.2007

05.12.2007

1

M/s.Dharti Dredging and Infrastructure(p) Ltd,Hyderabad

10.3.08

M/s.Dharti Dredging and Infrastructure(p) Ltd,Hyderabad

42,79,84,000/-

7 months

07-05-08.

06-12-08.

1538.09 lakhs

35.86%

 

 work in progress.

3.

Construction of North Cargo Berth - I

44.50crores

 

Publishing thro' News papers & Websites

Held on 19.2.2007

12.3.2007

3

1.M/s.Aster Teleservices Pvt ltd, Chennai

2.M/s. ITDC Ltd

3.M/s.Simplex

-

-

-

15 months

-

-

-

Letter issued to M/s. NLC requesting to deposit the anticipated cost for NCB-I Rs.90.76 crores

4.

Replacements of Equipments

 

 

 

a) Providing CR 80 Rail    in Berth I & II of VOC wharf

25.00 crores

 

 

 

2,30,50,000/--

02-08-2008.

Publishing thro' News papers & Websites

 

-do -

 

 

 

 

 

-

 

 

 

 

 

10.9.2008

 

 

 

 

 

 

-

 

1.     1.M/s.Rarefield Engineering Pvt,Ltd Tuticorin

2.     2.M/s.NematTraders ,Chennai

3.     3.M/s A.Ramanathan & Co,Trichy

4.     4.M/s Immanuel &co ,Tuticorin    

 

 

 

-

-

 

 

 

 

-

 

 

 

 

 

M/s.A.Ramanathan & Co, Trichy

 

 

 

 

 

Rs.

2,84,97,530/-

 

 

 

 

 

6 months

 

 

 

 

 

05.11.08

 

 

 

 

 

04.5.2009

 

 

 

 

 

-

      Supply order issued.

 

 

 

 

Work in progress

5.

 

 

 

 

Repair  and Rehabilitation works to Korampallam surplus Bridge and Rail over Bridge in Tuticorin Port Trust

1.57Crores

04-03-08

Publishing thro' News papers & Websites

-

-

-

-

-

-

-

-

-

-

-

Revised estimate for Rs.1.75 Crores sent to A/D for concurrence.

6.

“Deepening of channel and basin to cater to 12.80m draught vessels at Tuticorin Port Trust ”

Rs 538 Crores

20-06-08

Publishing thro' News papers & Website

-

29.9.08

-

1.M/s.Universal Dredging & Reclamation corporation ltd, Marutious.

2.M/s.Malisial Maritime Dredging Corporation- Vijay Nirman Company- JV Chennai.

-

-

-

14 months

-

-

-

Price bid opened on 20.12.2008. and under process.

7.

Widening and strengthening of Link road with bituminous concrete at TPT

Rs 2.23 Crores

Publishing thro' News papers & Website

02.7.08

11.7.08

2

1) M/s. Ramanathan & Co

2) M/S Immanuel & Co

08.8.08.

 M/S Immanuel & Co

Rs 2,21,84,415/-

5 Months.

13.8.08

12.01.09.

166 lakhs

75.11%

Work  in progress

 

 

 

 

 

 

 

 

 

 

Sl

No

 

Name of work

Sanctioned value of work with date of approval

 

Mode of tender Enquiry

Pre-bid tender status

 

Last date of receipt of tender

No of tenderers responded

Name of the tenderers technically

pre-qualified

Reference to work order

 

Name of the Contractor

Value of Contract

Period of contract

Dt. of commencement

Scheduled dt of completion

% of expre. status

Remarks

8

Strengthening of Road from V.O.C Statue to Blue gate passing through I.O.C Road leading to Hare Island and Qt rs road and burial ground in Tuticorin Port.

Rs.3.23crores

Publishing thro'News Paper&Website

-

05/12/08

2

1.M/s.Ramanathan&Co

 

2.M/s.Immanuel&Co

 

 

 

 

 

 

 

Price Bid opened on15.12.08and Tender under process

 

 

 

 

 

 

9

 

Construction Barge Jetty for lighter age operation in the eastern side of Coal stack yard

 

 

17.46Crores

Publishing thro'News paper &Website

_

_

_

_

_

_

_

__

_

_

_

Tender will be opened on 08.01.09

 

10

Construction of 3rd floor in the Administrative building at Tuticorin Port Trust

Rs.2.50 crores

-do-

-

-

-

-

-

-

-

-

-

-

-

Tender will be opened on  31.12.2008

11

Development of container stack yard at Tuticorin Port Trust

Rs.7.10 crores

-do-

-

-

-

-

-

-

-

-

-

-

-

Tender will be opened on07.01.2009