DETAILS OF CONTRACT CONCLUDED FOR WORKS COSTING MORE THAN Rs.5.00 CRORES INCLUDING STAGE PROGRESS UPTO DECEMBER, 2011
|
Sl No |
Name of work |
Sanctioned value of work with date of approval
|
Mode of tender Inquiry |
Pre-bid tender status
|
Last date of receipt of tender |
No of tenderers responded |
Name of the tenderers technically pre-qualified |
Reference to work order
|
Name of the Contractor |
Value of Contract |
Period of contract |
Dt. of commencement |
Scheduled dt of completion |
% of expdr. status (Rs. In Lakhs) |
Remarks |
|
1. |
Construction of Berth No.9 |
4000 Lakhs 21.7.2006
|
Publishing thro' News papers & Websites |
04.8.06 |
14.8.06 |
5 |
1.M/s.ITDC Pvt Ltd, Kolkatta
|
17.11.06 |
M/s.ITDC ltd, Kolkatta |
4457 Lakhs |
15 months |
02.12.06 |
14-11-08 Extended up to 30.06.2011 |
3949.32
88.60% |
Contract period extended upto 31.12.2011 |
|
2. |
Construction of North Cargo Berth - I |
Rs 4950 Lakhs
|
Publishing thro' News papers & Websites |
23.06.09 |
17.07.09 |
7 |
1. M/S Afcons, Mumbai 2. M/S Simplex, Chennai 3. M/S ITD Cementation, Kolkatta 4. M/S Vijay Nirman, Chennai 5. M/S Marg Ltd. Chennai 6. M/S Sys – Aster Chennai |
|
M/S Sys – Aster Chennai |
Rs. 49.40 Crores |
- |
- |
- |
1615.64 32.70% |
Work order issued to M/S Aster (JV), Chennai, for Rs. 49.40 Crores on 18.01.2010. Period of completion is 20 months from the date of issue of work order. Work commenced on 15.02.2010 and in progress. |
|
3.. |
Development of North Cargo Berth- II for handling bulk Cargoes under DBFOT basis |
Rs 33216Lakhs Board approved on 06.07.2007 |
P.P.P.Mode |
|
- |
- |
- |
- |
- |
- |
- |
- |
- |
24.85
|
******** |
|
|
******** LOA issued to M/s. ABG Bulk Handling Private Limited on 12.08.2010. Concession Agreement signed on 11.09.2010. Work order issued for the appointment of Independent Engineer for the project to M/S. Consulting Engineering Services, New Delhi on 28.02.2011. Preliminary survey completed. Design report submitted to the Independent Engineer by the concessioner. The survey work for fixing the alignment of conveyor from berth to stack yard at hare island completed. The concessioner submitted application to TNPCB for obtaining consent for the project. Kick off meeting with concessioner and IE held on 08.06.2011. |
||||||||||||||
|
4 |
“Deepening of channel and basin to cater to 12.80m drought vessels at Tuticorin Port Trust ” |
Rs 53800 Lakhs 20-06-08 |
Publishing thro' News papers & Website |
20.08.09 |
07.09.09 |
- |
1.M/s.Jan De Nul, Dredging India Pvt Ltd., 2.M/s.Dredging Inernational NV-VAN oord dredging and Marine contractors. 3.M/s.Boskalis Internationals b.v |
E(C) / F 59 / 10 / Projects / 2010 / D. 3919 Dated: 28.10.2010 |
M/s.Jan De Nul, Dredging India Pvt Ltd |
RS. 465,47,56,517 / - |
18 Months |
- |
- |
44,981.44 96.63% |
Work is nearing completion. |
|
5 |
Construction of Rubble Protection Bund in Tuticorin Port Trust |
Rs. 9.60 Lakhs |
Publishing thro' News papers & Website |
29.04.10 |
31.05.10 |
Two |
1. M/S. EMJAY Constructions, Chennai – 10 2. M/S. Aster Infratek, Chennai |
E(C) / F59 / 10 / PJT / RB / 2010 / D. 3880 (A) Dated: 27.10.10 |
M/S. EMJAY Constructions, Chennai – 10 |
RS. 10,34,17,500/- |
12 Months |
- |
- |
1085.51 104.96%
|
Work completed in all respect during, September, 2011 |