DETAILS OF CONTRACT CONCLUDED FOR WORKS COSTING MORE THAN Rs.5.00 CRORES  INCLUDING STAGE PROGRESS UPTO DECEMBER, 2011

 

Sl

No

 

Name of work

Sanctioned value of work with date of approval

 

Mode of tender Inquiry

Pre-bid tender status

 

Last date of receipt of tender

No of tenderers responded

Name of the tenderers technically

pre-qualified

Reference to work order

 

Name of the Contractor

Value of Contract

Period of contract

Dt. of commencement

Scheduled dt of completion

% of expdr.  status             (Rs. In Lakhs)

Remarks

1.

Construction of Berth No.9

4000 Lakhs

21.7.2006

 

Publishing thro' News papers & Websites

04.8.06

14.8.06

5

1.M/s.ITDC Pvt Ltd,

Kolkatta

 

17.11.06

M/s.ITDC ltd, Kolkatta

4457 Lakhs

15 months

02.12.06

14-11-08

Extended up to 30.06.2011

3949.32

 

88.60%

Contract period extended upto 31.12.2011

2.

Construction of North Cargo Berth - I

Rs 4950 Lakhs

 

Publishing thro' News papers & Websites

23.06.09

17.07.09

7

1. M/S Afcons, Mumbai

2. M/S Simplex, Chennai

3. M/S ITD Cementation, Kolkatta

4. M/S Vijay Nirman, Chennai

5. M/S Marg Ltd. Chennai

6. M/S Sys – Aster Chennai

 

M/S Sys – Aster Chennai

Rs. 49.40 Crores

-

-

-

1615.64

32.70%

Work order issued to M/S Aster (JV), Chennai, for   Rs. 49.40 Crores on 18.01.2010. Period of completion is 20 months from the date of issue of work order. Work commenced on 15.02.2010 and in progress. 

3..

Development of North Cargo Berth- II for handling bulk Cargoes  under DBFOT basis

Rs 33216Lakhs Board approved on 06.07.2007

P.P.P.Mode

 

-

-

-

-

-

-

-

-

-

24.85

 

********

 

******** LOA issued to M/s.  ABG Bulk Handling Private Limited on 12.08.2010. Concession Agreement signed on 11.09.2010. Work order issued for the appointment of Independent Engineer for the project to M/S. Consulting Engineering Services, New Delhi on 28.02.2011. Preliminary survey completed. Design report submitted to the Independent Engineer by the concessioner. The survey work for fixing the alignment of conveyor from berth to stack yard at hare island completed.  The concessioner submitted application to TNPCB for obtaining consent for the project. Kick off meeting with concessioner and IE held on 08.06.2011.

4

“Deepening of channel and basin to cater to 12.80m drought vessels at Tuticorin Port Trust ”

Rs 53800 Lakhs

20-06-08

Publishing thro' News papers & Website

20.08.09

07.09.09

-

1.M/s.Jan De Nul, Dredging India Pvt Ltd.,

2.M/s.Dredging Inernational NV-VAN oord dredging and Marine contractors.

3.M/s.Boskalis Internationals b.v

E(C) / F 59 / 10 / Projects / 2010 / D. 3919 Dated: 28.10.2010

M/s.Jan De Nul, Dredging India Pvt Ltd

RS.

 465,47,56,517    

/ -

18 Months

-

-

44,981.44

96.63%

Work is nearing completion.

5

Construction of Rubble Protection Bund in Tuticorin Port Trust

Rs. 9.60 Lakhs

Publishing thro' News papers & Website

29.04.10

31.05.10

Two

1. M/S. EMJAY Constructions,

 Chennai – 10

2. M/S. Aster Infratek, Chennai

E(C) / F59 / 10 / PJT / RB / 2010 / D. 3880 (A) Dated: 27.10.10

 M/S. EMJAY Constructions,

 Chennai – 10

RS. 10,34,17,500/-

12 Months

-

-

1085.51

104.96%

 

Work completed in all respect during, September, 2011